Restaurant Opening Checklist: What Must Be Done, and by When, in the Last 90 Days

Restaurant Opening Checklist: What Must Be Done, and by When, in the Last 90 Days

‍

A restaurant opening checklist only protects your opening date when every item on it has a deadline. Most late openings trace back to a handful of items with long lead times, such as health department plan review, a gas meter, an internet line, a liquor license or payment account approval, that were started a few weeks too late. Once one of those slips, the opening date slips with it, while rent and payroll keep running.

This checklist covers the last 90 days before opening and groups the work into seven workstreams: licenses and inspections, build-out and utilities, vendors and food cost, hiring and training, menu and pricing, technology and payments, and marketing with a soft opening. Each workstream has a deadline tag that says how many days before opening it must be finished. The day counts are a planning guide, not legal deadlines, and rules cited here are current as of November 2026, so confirm each requirement with your city, county and state. If you are taking over an existing business, work through our buying an existing restaurant checklist first, since the license, lease and equipment questions differ.

‍

How to Run the Checklist: One Owner per Workstream, One Date per Item

Pick a target opening date and call it Day 0. Count backward from there, so "Day 30" means thirty days before you open. Write that date at the top of every page, because every deadline below hangs from it.

Give each workstream one owner. In a small restaurant that may be you for most of them, with a chef or general manager taking menu and vendors. The point is that every item has a name next to it, so nothing sits in the gap between two people who each assumed the other was handling it.

Hold a short weekly review, around thirty minutes, where each owner reports only what is late or at risk. When an item with a long lead time slips, decide that day whether to push Day 0 or find a workaround. Moving the date early, before you announce it, is cheaper than moving it after invitations go out and staff are on payroll.

‍

Licenses, Permits and Inspections

Deadline tag: applications filed by Day 90 or earlier, and every final inspection passed with the operating permit in hand by Day 7.

This workstream has the longest lead times and the least control, because the schedule depends on government offices. Start it first and check on it every week.

  • Form your business entity with the state and get a free Employer Identification Number (EIN) from the IRS.
  • Register for state sales tax before your first sale, including soft-opening sales if you charge for food.
  • Apply for the city or county business license and confirm the zoning allows a restaurant at your address.
  • Submit plans to the health department for plan review if your jurisdiction requires it, and do this before construction starts.
  • Pull building, electrical, plumbing and mechanical permits for the build-out.
  • Schedule fire inspection, including the hood fire-suppression system and extinguishers.
  • Get your certificate of occupancy or equivalent sign-off for the space.
  • Book the health department's pre-opening inspection and receive the food establishment permit.
  • Apply for a liquor license if you plan to serve alcohol. In many places approval takes months, so file as early as your lease allows.
  • Apply for a sign permit if you are installing exterior signage.
  • Make sure at least one manager holds a food protection manager certification. The FDA Food Code, which most states adopt in some form, requires the person in charge to be a certified food protection manager.

Keep a binder or shared folder with every application, receipt and approval. Inspectors and landlords will ask for copies, and you will need them again when you renew.

‍

Build-Out, Utilities and Equipment

Deadline tag: construction finished and all utilities live by Day 21, with every piece of equipment installed and tested by Day 14.

Even if your space is a second-generation restaurant, plan on repairs, upgrades and at least one surprise behind a wall. Utility work often waits on outside companies, so order early.

  • Open or transfer gas, electric and water accounts. New service or meter changes can take weeks.
  • Order the internet line and a backup connection by Day 60. Installation dates fill up, and your payment system depends on them.
  • Have the hood and exhaust system cleaned, inspected and certified, along with the fire-suppression system.
  • Confirm grease trap or interceptor service and set a pumping schedule.
  • Start a pest control contract before food arrives, and keep the service reports.
  • Set up trash, recycling and, where required, food-waste pickup.
  • Run the walk-in cooler, reach-ins and freezers for at least 72 hours and log temperatures before you stock them.
  • Test every burner, fryer, oven, rice cooker and dish machine at full load. Call service companies while warranties and installers are still on site.
  • Install handwashing signs, thermometers in every cooler and first-aid supplies.

Walk the space during a mock service with staff in position. Problems like a door that swings into the pass or a missing outlet at the expo station are cheap to fix before Day 14 and expensive afterward.

‍

Vendors, Ordering and Food Cost

Deadline tag: vendor accounts approved by Day 30, and the first full delivery received three to four days before the soft opening.

Vendor credit applications, delivery schedules and minimum orders all take time to settle. Asian restaurants often need both a broadline distributor and one or more specialty suppliers for items such as rice, noodles, sauces and frozen dumplings, so plan for several accounts.

  • Choose a primary distributor and specialty suppliers, and submit credit applications.
  • Confirm delivery days, cutoff times for orders and minimum order sizes.
  • Build an order guide with item codes, pack sizes and par levels for your expected first-week volume.
  • Line up a backup source for the few items your menu cannot run without.
  • Cost every recipe from real vendor prices so menu pricing rests on numbers, not guesses.
  • Order smallwares, to-go packaging, cleaning chemicals, gloves and paper goods.
  • Write a receiving procedure: who checks deliveries, how temperatures are taken and how shorts are credited.

Order lighter than you think for the soft opening and the first week. It is easier to add a delivery than to throw out product because the menu changed after the first few services.

‍

Hiring, Paperwork and Training

Deadline tag: managers hired by Day 60, hourly staff hired by Day 21, and training run during the final 14 days.

Hiring takes longer than most owners plan for, and the paperwork has fixed federal deadlines. Set up payroll before anyone's first shift, including paid training days.

  • Post jobs and interview early enough to make offers by Day 21.
  • Complete Form I-9 for every hire. The employee completes Section 1 by the first day of work, and you complete Section 2 within three business days of that first day.
  • Collect federal Form W-4 and any state withholding forms.
  • Report new hires to your state's new hire directory. Federal law sets a 20-day limit, and some states require it sooner.
  • Buy workers' compensation insurance, which most states require once you have employees.
  • Hang the required federal and state labor law posters.
  • Confirm food handler cards where your city or state requires them.
  • Write an employee handbook that covers tips, breaks, scheduling and POS logins. Our guide to a restaurant employee handbook lists the clauses restaurants most often miss.
  • Schedule training by station, with recipe cards and service steps in every language your team speaks.

Plan at least two full practice services before the soft opening. Staff learn the menu faster by cooking and serving it than by reading it.

‍

Menu, Recipes and Pricing

Deadline tag: menu and prices locked by Day 30, so menus can be printed, photographed and loaded into the POS.

Changing the menu late creates work across every other workstream: new vendor items, new recipe cards, reprinted menus and reprogrammed buttons. Set a firm lock date and hold to it.

  • Finalize every dish, its portion size and its plating.
  • Write recipe cards with photos, weights and cook times.
  • Calculate plate cost for each item and set prices with a target food cost in mind.
  • Document allergens for each dish so staff can answer guest questions accurately.
  • List every modifier, such as spice level, protein swaps and add-ons, with its price.
  • Prepare menu translations if you serve guests in more than one language.
  • Photograph dishes for online ordering, delivery apps and social media.
  • Send printed menus and table materials to the printer by Day 21.

Launch with a slightly smaller menu than your final plan. You can add dishes once the kitchen is running smoothly.

‍

Technology, Payments and the POS

Deadline tag: payment account approved by Day 30, POS and network installed by Day 14, and a full test of orders, payments and refunds finished by Day 7.

For device-by-device detail on terminals, printers and kitchen screens, use our point of sale hardware checklist for a new location. This list covers the setup work around the hardware.

  • Apply for your payment processing account early, since underwriting can ask for documents you need time to gather.
  • Build the menu in the POS, including modifiers, combos and kitchen routing for each item.
  • Set tax rates, tip options and service charge rules, and confirm them with your accountant.
  • Create staff logins with permission levels so only managers can void, discount or refund.
  • Connect online ordering and delivery menus, and match their prices and item names to your POS.
  • Run test card payments, refunds and cash drawer closes, and confirm the first deposit reaches your bank account.
  • Test what happens when the internet drops, so staff know the backup steps.

Many POS providers help with this setup. Chowbus's POS for new restaurants, for example, includes professional network installation, on-site hardware setup, team training and 24/7 support, which takes several of these items off your own list. Whichever provider you choose, ask for their installation and training dates in writing and work backward from Day 14.

‍

Marketing and the Soft Opening

Deadline tag: online listings claimed by Day 60, an invite list ready by Day 14, and the soft opening held three to seven days before the public opening.

Guests cannot visit a restaurant they cannot find. Get your listings up early and use the soft opening as a dress rehearsal with real guests.

  • Claim and verify your Google Business Profile. Verification can take days or longer, so start early.
  • Claim your listings on Yelp and the review sites your guests use.
  • Set up social media accounts and post construction and menu previews.
  • Put up "coming soon" signage with your opening month.
  • Reach out to local community groups and media, including Chinese-language outlets and group chats if they serve your audience.
  • Build an invite list of neighbors, nearby businesses, friends and family for soft opening nights.
  • Prepare a simple feedback card or form for soft opening guests.
  • Plan the public opening event. Our list of restaurant grand opening ideas has options for different budgets.

Run at least two soft opening services, ideally one lunch and one dinner, with full staff on the schedule. Afterward, meet with the team, fix the top problems and adjust prep levels before you open to the public.

Frequently Asked Questions

Q1: What is a restaurant opening checklist?

It is a list of every task that must be done before a restaurant serves its first public guest, from licenses and inspections to hiring, vendors, menu, technology and marketing. A useful version assigns each task an owner and a deadline counted back from the opening date, so long lead-time items start early enough.

Q2: How far ahead should I start my restaurant opening checklist?

Start at least 90 days before your target opening, and earlier if you need a liquor license or major construction. Permits, utility work and payment account approval have lead times you cannot shorten. Starting late is the most common reason opening dates slip.

Q3: Is the checklist different when buying an existing restaurant?

Yes. When you buy an existing restaurant, many permits do not transfer automatically, and you need to review the lease, equipment condition, existing contracts and the POS setup. Those items come before the opening checklist here, which assumes you are setting up operations in a space you control.

Q4: Which opening costs do owners most often leave off the checklist?

Common gaps include utility deposits, permit and inspection fees, wages for paid training days, opening inventory, soft opening food and packaging, and spare equipment. These rarely appear in the build-out budget but all come due before the first sale. List them as their own budget lines with real quotes.

Q5: What if the health inspection is delayed a week before opening?

You cannot serve the public without the permit, so move the public opening and tell staff and guests right away. Use the extra days for more training services, and ask the health department whether an earlier inspection slot can open up. Leaving a week of buffer between the inspection and Day 0 helps avoid this.

Q6: What should I do first if I have just signed a lease?

Set Day 0, write the seven workstreams on one page and assign an owner to each. Then call the health department and the building department to learn their review times, and order the internet line and utilities that same week. Those answers will tell you whether your opening date is realistic.

A restaurant opening checklist works when it is grouped by who owns the work and dated backward from the day you open. Permits, utilities, vendor accounts, hiring paperwork, the menu lock, payment approval and listings each have their own lead time, and the earlier you know those dates, the fewer surprises reach your opening week.

Set your Day 0 this week, give every workstream an owner, and review what is late every Monday until you open. Confirm each legal requirement with your local authorities, keep a week of buffer before the public opening, and treat the soft opening as the final test of everything on the list.